The following Road Closure has been Confirmed:
Outage: Test Lab LN2 System - Install Rental LN2 system to provide nitrogen gas
Proposed By: Ronald Bartek
Start Time: 02/26/2018 07:00
End Time: 02/26/2018 18:00
Description/Impacts:
Will be installing Rental equipment to provide backup capacity to the present Test Lab LN2 leaking system to prevent gas/LN2 interruptions to the Test Lab, TED, EEL, HDIce, and education department. The asphalt area between the Test Lab and the TED building will be congested with trucks, cranes and workers that will setting up the rental system.
Impacted Areas:
TEDF Parking
Cornell U. Road
For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=2
More information about the Fac_outages