[Utility Outage] Scheduled Power Outage - 01/26/2018 06:00
j. willoughby
jasonw at jlab.org
Wed Jan 24 08:09:58 EST 2018
The following Power Outage has been Confirmed:
Outage: test Lab DP-LAB-10
Proposed By: j. willoughby
Start Time: 01/26/2018 06:00
End Time: 01/26/2018 07:00
Description/Impacts:
Remove power from DP-LAB-10. This will remove all power from the Injector test Cave and the cleanroom beside the cave entrance.
Impacted Areas:
Bldg 58: Test Lab
For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=1