The following Power Outage has been Completed:
Outage:      test Lab DP-LAB-10
Proposed By: j. willoughby
Start Time:  01/26/2018 06:00
End Time:    01/26/2018 07:00
Description/Impacts:
Remove power from DP-LAB-10.  This will remove all power from the Injector test Cave and the cleanroom beside the cave entrance.
Impacted Areas:
	Bldg 58: Test Lab