The following Power Outage has been Completed:
Outage:      ESH&Q UPS Power Outage
Proposed By: J. Willoughby
Start Time:  06/08/2018 06:00
End Time:    06/08/2018 08:00
Description/Impacts:
Remove power from thhe UPS panel and all lighting in the ESHQ building, to repair the lighting controller.  This will remove all 208/120 power from all UPS receptacles and circuits (labeled with red receptacles)
Impacted Areas:
	Bldg 52: EHS&Q Building