[Utility Outage] Completed Water Outage - 09/24/2018 08:20
Ron Bartek
bartek at jlab.org
Fri Sep 28 13:58:17 EDT 2018
The following Water Outage has been Completed:
Outage: PSB Bldg.-Interrupt safety shower operation to install water hammer arrestors
Proposed By: Ron Bartek
Start Time: 09/24/2018 08:20
End Time: 09/28/2018 17:00
Description/Impacts:
Test Lab PSB Bldg - Will interrupt the operation of the safety showers to install water hammer arrestors on incoming city water feed line for each shower. Only one safety shower will be interrupted at a time leaving the second safety shower operational.
Impacted Areas:
Bldg 58: Test Lab
For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=2