[Utility Outage] Scheduled Power Outage - 04/24/2019 07:00

Paul Powers powersp at jlab.org
Fri Apr 19 08:19:09 EDT 2019


The following Power Outage has been Confirmed:

Outage:      SWBD LS1
Proposed By: Paul Powers
Start Time:  04/24/2019 07:00
End Time:    04/25/2019 23:59

Description/Impacts:
Work to replace existing switchboard.  Could extend into Friday.

Impacted Areas:
	Bldg 02: South LINAC
	Bldg 40: West Arc Service
	Bldg 56: West Arc Service
	Bldg 68: West Arc Service
	Bldg 82: South Extractor Service

For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=8