The following Power Outage has been Confirmed:
Outage:      Transformer T6 Replacement
Proposed By: Paul Powers
Start Time:  05/01/2019 07:00
End Time:    05/01/2019 14:00
Description/Impacts:
Transformer and Power outage to replace leaking transformer.  Complete Power Outage Bldg 92, 91, the little tent bldg, Hall B Truck Ramp Utilities (Hall B utility Power including lighting).  It also secures LCW for all three Halls and A/C for Hall B.
Impacted Areas:
	Bldg 91: Beam Dump Cooling Building A
	Bldg 92: Service Building
	Bldg 94: Experimental Hall B
	Bldg 96: Experimental Hall C
	Bldg 101: Experimental Hall A
For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=11
    
    