[Utility Outage] Scheduled HVAC Outage - 12/09/2019 06:00
    Mike Sprouse 
    msprouse at jlab.org
       
    Fri Dec  6 10:47:18 EST 2019
    
    
  
The following HVAC Outage has been Confirmed:
Outage:      Building 90 Heating Hot Water Pump Replacement
Proposed By: Mike Sprouse
Start Time:  12/09/2019 06:00
End Time:    12/09/2019 17:00
Description/Impacts:
Must replace the leaking hot water pump which provides heat for the EEL building : will require significant piping modifications to allow new pump installation. Working in room 102 (Hall C fab shop) and outside building SE corner. *Please avoid these areas during the task.
**Affects ALL areas of building 90 (except offices on 2nd floor NW corner) : No HEAT until repair is complete. Valves which supply hot water from the Test Lab will be isolated Sunday evening to allow the piping (and water) to cool to a safe temperature for work on Monday AM.
***This is NOT an optional repair - pump is leaking HOT water.
Forecast temperature for Monday is 66*F  
  
Impacted Areas:
	Bldg 90: Experimental Equipment Lab
For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=2
    
    
More information about the Fac_outages
mailing list