The following Power Outage has been Confirmed:
Outage:      CTF work
Proposed By: Todd Kujawa
Start Time:  01/06/2020 08:00
End Time:    01/10/2020 16:00
Description/Impacts:
Rolling Outages at the CTF during January 6-10. Coordination has been made with Cryo and will continue on a daily basis during the week.
Impacted Areas:
	Bldg 57: Cryogenic Test Facility
For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=1
    
    