[Utility Outage] Proposed Power Outage - 07/23/2019 07:00
John Riesbeck
riesbeck at jlab.org
Fri Jul 19 09:53:46 EDT 2019
The following Power Outage has been Proposed:
Outage: Bldg 12 Fwing power outage
Proposed By: John Riesbeck
Start Time: 07/23/2019 07:00
End Time: 07/23/2019 11:00
Description/Impacts:
Remove power from electrical panel ERPB which includes the following circuits:
SUMP PUMP - ELEVATOR
ELEVATOR LTS & CONTROL
REC. ELEVATOR MECHANICAL ROOM
REC. RM 104
REC. RM 105
REC. RM 105
REC. RM 105
REC. RM 105
DOOR CONTROL
SMOKE DAMPER
FIRE SHUTTER
SPARE ABOVE THE CEILING
F303 TWIST-LOCK
F203 TWIST-LOCK
F103 TWIST-LOCK
FIRE ALARM STROBE
ELEVATOR SHUNT TRIP
REC. RM 204
REC. RM 205
REC. RM 205
REC. RM 205
REC. RM 205
REC. RM 304
REC. RM 305
REC. RM 305
REC. RM 305
REC. RM 305
Impacted Areas:
Bldg 12: CEBAF Center
For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=2
More information about the Fac_outages
mailing list