[Utility Outage] Scheduled Power Outage - 03/23/2019 07:00
Paul Powers
powersp at jlab.org
Mon Mar 18 16:14:46 EDT 2019
The following Power Outage has been Confirmed:
Outage: EEL and CEBAF Center
Proposed By: Paul Powers
Start Time: 03/23/2019 07:00
End Time: 03/24/2019 17:00
Description/Impacts:
Power to CEBAF Center and EEL will be secured at 7 AM. This outage will NOT affect the HPC in the Data Center. Power to all Areas EXCEPT the Data Center will be secured. Emergency Power will be provided for the Kitchen Freezer and Refrigerator in the new addition (rear of Building). Power to CEBAF Center including F-Wing will be restored at the end of the day (Saturday). Power to the EEL will be restored at the end of the day on Sunday. ALL OF THIS IS SUBJECT TO WEATHER.
Impacted Areas:
Bldg 12: CEBAF Center
Bldg 90: Experimental Equipment Lab
For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=2
More information about the Fac_outages
mailing list