[Utility Outage] Completed Power Outage - 03/22/2019 10:00
    J. Willoughby 
    jasonw at jlab.org
       
    Fri Mar 22 14:18:01 EDT 2019
    
    
  
The following Power Outage has been Completed:
Outage:      LERF - Panel U400
Proposed By: J. Willoughby
Start Time:  03/22/2019 10:00
End Time:    03/22/2019 12:00
Description/Impacts:
Remove power from U400 to tie in feed for compressor enclosure.  This will impact the following:
120/208
Receptacles in Room 107, 201, 104, 105 PIT, 100, 101, 102
Water Heater
120 Elevator Circuit
Video Monitor Lobby
Lobby Lights
AC-1 indoor and outdoor
Impacted Areas:
	Bldg 18: Free Electron Laser
For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=3
    
    