[Utility Outage] Completed Power Outage - 04/24/2019 07:00
    Paul Powers 
    powersp at jlab.org
       
    Thu May  9 14:41:39 EDT 2019
    
    
  
The following Power Outage has been Completed:
Outage:      SWBD LS1
Proposed By: Paul Powers
Start Time:  04/24/2019 07:00
End Time:    04/25/2019 23:59
Description/Impacts:
Work to replace existing switchboard.  Could extend into Friday.
Impacted Areas:
	Bldg 02: South LINAC
	Bldg 40: West Arc Service
	Bldg 56: West Arc Service
	Bldg 68: West Arc Service
	Bldg 82: South Extractor Service
For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=8
    
    