[Utility Outage] Completed Power Outage - 09/19/2019 13:31
    John Riesbeck 
    riesbeck at jlab.org
       
    Fri Sep 20 09:36:41 EDT 2019
    
    
  
The following Power Outage has been Completed:
Outage:      SA-2 switchboard outage
Proposed By: John Riesbeck
Start Time:  09/19/2019 13:31
End Time:    09/19/2019 13:31
Description/Impacts:
L38 - LCWP -4			
MOTOR CONT. CNT SOUTH ACCESS				
PANEL SA-L			
TRANSF. E6-T1 (112KVA) PANEL SA-PP1
PUMP S-1 (38 - LCW -2)					
PNL SAL3 PUMP RM					
TRANSF. S4-T4 PANEL SA-P					
TRANSF. E6-T2 (75KVA) PANEL SA-PP2			
			
			
Impacted Areas:
	Bldg 38: South Access
For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=2
    
    