The following Power Outage has been Completed:
Outage:      cooler outlet
Proposed By: todd kujawa
Start Time:  09/23/2019 14:00
End Time:    09/23/2019 15:00
Description/Impacts:
outage for panels PP101 and PP101A.
affected is mostly kitchen area and few lobby receptacles.
Impacted Areas:
	Bldg 12: CEBAF Center