[Utility Outage] Proposed Power Outage - 08/19/2020 07:00
John Riesbeck
riesbeck at jlab.org
Mon Aug 17 16:46:57 EDT 2020
The following Power Outage has been Proposed:
Outage: CHL -TP circuit #18 outage
Proposed By: John Riesbeck
Start Time: 08/19/2020 07:00
End Time: 08/19/2020 12:00
Description/Impacts:
turn off the branch circuit feeding General Purpose outlets at the CHL cooling tower.
Impacted Areas:
Bldg 08: Central Helium Liquefier
For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=3
More information about the Fac_outages
mailing list