[Utility Outage] Completed Power Outage - 12/09/2020 13:30
Ed Winslow
winslow at jlab.org
Thu Dec 10 12:54:36 EST 2020
The following Power Outage has been Completed:
Outage: Physics Storage B72
Proposed By: Ed Winslow
Start Time: 12/09/2020 13:30
End Time: 12/09/2020 15:30
Description/Impacts:
Remove power from panel 72-PSB-L1. This will remove power from the following:
Panel 72-PSB-P1
- All 120V house power receptacles
- DDC control Panel
- Gas Heat Rec
- ACS Controls
- Dampers
- Fire Alarm Control Panel
- 208/120Y outlets/receptacles
480V welding receptacles
Roll-Up Door
Exhaust Fans 1&2
Interior & Exterior Lighting
Impacted Areas:
Bldg 72: Physics Storage
For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=4