[Utility Outage] Scheduled Power Outage - 12/28/2020 09:00
    powersp 
    powersp at jlab.org
       
    Tue Dec 15 11:36:50 EST 2020
    
    
  
The following Power Outage has been Confirmed:
Outage:      Power Outage Test Lab-TED-CTF
Proposed By: powersp
Start Time:  12/28/2020 09:00
End Time:    12/28/2020 16:00
Description/Impacts:
Rolling Power outages for Electrical PM.  All outages will be very brief as we exercise breakers.  We will start int he CTF and progress to the Test Lab and TED.  
Impacted Areas:
	Bldg 55: TED Building
	Bldg 57: Cryogenic Test Facility
	Bldg 58: Test Lab
For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=5
    
    
More information about the Fac_outages
mailing list