[Utility Outage] Proposed Power Outage - 02/25/2020 07:45
Todd Kujawa
kujawa at jlab.org
Tue Feb 25 07:48:46 EST 2020
The following Power Outage has been Proposed:
Outage: CHL# & CHL4 transformer work
Proposed By: Todd Kujawa
Start Time: 02/25/2020 07:45
End Time: 02/25/2020 07:45
Description/Impacts:
CHL4 will be turned off on Monday March 2 and then later in the week on Wednesday March 4 CHL4 will be turned back on and CHL3 turned off. On Thursday March 5 CHL3 will be turned back on.
This work is to support the oil processing of these transformers.
Impacted Areas:
Bldg 08: Central Helium Liquefier
For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=2