The following Power Outage has been Proposed:
Outage:      CEBAF Center - EEL - Test Lab - TED Power Outage
Proposed By: powers
Start Time:  10/17/2020 07:00
End Time:    10/17/2020 17:00
Description/Impacts:
Power outage to all 4 building to perform electrical PM.  All systems to be affected EXCEPT for Computer Center.  Call Paul Powers 876-1780 if there is a problem and you want your area to be excluded.  Schedule a meeting with Paul on Mon-Wed to walkdown your area of concern to make sure it is not turned off.
Impacted Areas:
	Bldg 12: CEBAF Center
	Bldg 55: TED Building
	Bldg 57: Cryogenic Test Facility
	Bldg 58: Test Lab
	Bldg 90: Experimental Equipment Lab
For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=1
    
    