[Utility Outage] Completed Power Outage - 04/02/2021 06:00

J. Willoughby jasonw at jlab.org
Fri Apr 2 09:38:01 EDT 2021


The following Power Outage has been Completed:

Outage:      B98 - BSY Outage
Proposed By: J. Willoughby
Start Time:  04/02/2021 06:00
End Time:    04/02/2021 09:00

Description/Impacts:
Remove power from the entire B98  to verify connections for the energizing of the new XFMR T14.  This will impact B98 and the BSY area.  All 480-120 power will be off.  Emergency panel is not impacted.

Impacted Areas:
	Bldg 98: Physics Fabrication Building

For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=1



More information about the Fac_outages mailing list