[Utility Outage] Completed Power Outage - 04/22/2021 15:00

kujawa kujawa at jlab.org
Thu Apr 22 15:27:04 EDT 2021


The following Power Outage has been Completed:

Outage:      W3-P outage (TODAY - Thursday at 3pm)
Proposed By: kujawa
Start Time:  04/22/2021 15:00
End Time:    04/22/2021 16:00

Description/Impacts:
Secure power to panel W3-P in B56 to change out a suspect circuit breaker.

3pole 30amp circuit #2 (REC. TUNNEL)

Work has been discussed with Operations (Steve Suhring)

Impacted Areas:
	Bldg 56: West Arc Service

For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=1