The following Power Outage has been Completed:
Outage: Panel CHEMP 2
Proposed By: kujawa
Start Time: 07/16/2021 08:00
End Time: 07/16/2021 10:00
Description/Impacts:
Panel CHEMP2 needs to be off for about 1hr- no longer than 2hrs to add in new circuits.
Impacted Areas:
Bldg 97: Counting House
For more details, visit the webpage listed below: