The following Road Closure has been Completed:

Outage:      Cooling Tower Repairs - Crane set up on Cornell U Rd. 
Proposed By: Mike Sprouse
Start Time:  03/09/2021 07:30
End Time:    03/09/2021 15:00

Description/Impacts:
Lifting 2 fan motors over the fence into CT58.
During cooling tower repairs on CT58, there will be a crane set-up on Cornell U Rd. just W of the turn at "Gilligan's Island". This will not stop all traffic flow to TL or TED but will not allow the usual circular traffic flow around the island = large trucks may have difficulty navigating the area. 
*No Bldg. 58  N2 deliveries are scheduled for 3/9/21 (per CRYO).


Impacted Areas:
	Bldg 55: TED Building
	Bldg 58: Test Lab

For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=2