The following Power Outage has been Completed:

Outage:      TED HighBay Outage EVSE
Proposed By: J. Willoughby
Start Time:  12/22/2022 10:00
End Time:    12/22/2022 13:00

Description/Impacts:
Update:  Shifted time to 10AM to accommodate building occupants' scheduling


Remove power from TED Highbay panel 55-DP-1-6A to tie in EVSE transformer.  This impacts all 480 and 120/208 circuits in the entire TED Highbay.  Lights and data outlets will still be active, but all other circuits will be off.

If outage is not ready ready by Thursday 12/22 - makeup outage date will be Monday 12/26

Impacted Areas:
	Bldg 55: TED Building