[Utility Outage] Completed Power Outage - 03/10/2022 07:00
    J. Willoughby 
    jasonw at jlab.org
       
    Fri Jun 10 14:16:03 EDT 2022
    
    
  
The following Power Outage has been Completed:
Outage:      Hall ABC Meter Installation
Proposed By: J. Willoughby
Start Time:  03/10/2022 07:00
End Time:    03/11/2022 15:00
Description/Impacts:
Atlis 24070
Remove power from the following for meter installation:
97-SB-B3
97-SB-B3A
97-SB-B3A
This will remove power from Halls ABC and Counting House.  Outage is intended to only run 3/10 from 7AM to 3PM - power restored before COB and 3/11 is reserved for finalizing anything not completed on 3/10.
Impacted Areas:
	Bldg 94: Experimental Hall B
	Bldg 96: Experimental Hall C
	Bldg 97: Counting House
	Bldg 101: Experimental Hall A
For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=43
    
    
More information about the Fac_outages
mailing list