The following Power Outage has been Completed:
Outage:      B12 and B55 switching exercise
Proposed By: kujawa
Start Time:  05/14/2022 07:00
End Time:    05/14/2022 13:00
Description/Impacts:
Annual switching PMs for B12 and B55 electrical circuits.
Computer Center will not be switched.
All other circuits will lose power momentarily while being switched off and then back on.
Impacted Areas:
	Bldg 12: CEBAF Center
	Bldg 55: TED Building
For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=6
    
    