[Utility Outage] Proposed Power Outage - 10/05/2022 09:00

J. Willoughby jasonw at jlab.org
Mon Sep 26 06:32:40 EDT 2022


The following Power Outage has been Proposed:

Outage:      Guardhouse Outage
Proposed By: J. Willoughby
Start Time:  10/05/2022 09:00
End Time:    10/05/2022 11:00

Description/Impacts:
Tentative outage.  Remove power from the entire guardhouse building to install power meters.  It is intended to keep the network rack and badge reading station operational during this outage.  All other items will be off during this outage.

Impacted Areas:
	Bldg 51: Guard House

For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=7