[Utility Outage] Completed Power Outage - 07/27/2023 13:00
Paul Powers
powersp at jlab.org
Tue Aug 8 07:51:36 EDT 2023
The following Power Outage has been Completed:
Outage: Injector Bldg 53 - Panel IB-PP3 Work to replace damaged 30 A 3 pole ckt brkr
Proposed By: Paul Powers
Start Time: 07/27/2023 13:00
End Time: 07/27/2023 15:15
Description/Impacts:
Power outage to replace damaged circuit breaker ckts 13, 15, 17. Please remove all LOTO BEFORE 12 Noon. We can't start before LOTO is removed.
Impacted Areas:
Bldg 53: Injector Service
For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=2
More information about the Fac_outages
mailing list