The following Power Outage has been Proposed:

Outage:      Hall A Berm Conduit Relocation
Proposed By: todd kujawa
Start Time:  12/21/2023 07:00
End Time:    12/21/2023 15:00

Description/Impacts:
Panel MDP-BA will need turned off when it comes time to change over to the new circuit. This panel feeds the Hall A air-conditioning unit but the Hall shouldn't be affected because of the lower outside temperatures and also the Hall has a backup unit also.
Talking with FM mechanical, the main AC unit being off for less than 8 hours will not be an issue.
The start date is just a filler right now; actual date will be determined as the job gets closer to the end.

Impacted Areas:
	Bldg 101: Experimental Hall A

For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=3