The following Power Outage has been Proposed:

Outage:      UPS-P1 outage
Proposed By: John Riesbeck
Start Time:  01/05/2023 08:00
End Time:    01/05/2023 16:00

Description/Impacts:
Remove power at UPS to change batteries, this will require intermittent loss of power to Panel UPS-P1

LOAD DESCRIPTION					
PYROLYSER				
UPS REC. RM 31 EAST WALL			
UPS REC. RM 31 SOUTH WALL			
UPS REC. RM 31 WEST WALL			
UPS REC. RM 31 NORTH WALL			
UKPS REC. RM 20 EAST WALL			
UPS REC. RM 20			
REC. DATA RACK			
REC. PYROLYSER COMPRESSOR			
LIGHTING CONTROL PANEL POWER		
UPS REC. RM 22 SOUTH WALL			
UPS REC. RM 22 SOUTH WALL			
UPS REC. RM 22 EAST WALL			
UPS REC. RM 22 EAST WALL			
UPS REC. RM 22 SOUTH WALL			
UPS REC. RM 22 EAST WALL			
UPS REC. RM 22 EAST WALL			
UPS REC. RM 22 WEST WALL			
UPS RE. RM 22 WEST WALL			
SPD			
			
			
	


Impacted Areas:
	Bldg 52: EHS&Q Building