[Utility Outage] Completed Power Outage - 01/09/2023 09:00
J. Willoughby
jasonw at jlab.org
Mon Jan 9 15:02:45 EST 2023
The following Power Outage has been Completed:
Outage: CTF MCC Outage
Proposed By: J. Willoughby
Start Time: 01/09/2023 09:00
End Time: 01/09/2023 12:00
Description/Impacts:
Remove power from secondary side XFMR Sub3R. This will remove 480 power to the compressor MCC in the CTF. Outage is needed to tie in final connections to the meter for the MCC.
Impacted Areas:
Bldg 57: Cryogenic Test Facility
For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=5