[Utility Outage] Completed Water Outage - 07/11/2023 08:00
    David Sulouff 
    sulouff at jlab.org
       
    Wed Jul 12 10:40:01 EDT 2023
    
    
  
The following Water Outage has been Completed:
Outage:      B60 Water Meter Installation
Proposed By: David Sulouff
Start Time:  07/11/2023 08:00
End Time:    07/11/2023 10:00
Description/Impacts:
Water Meter Installation will require a water outage for roughly 2 hours to drain and modify piping.
Impacted Areas:
	Bldg 60: Chiller Utility Plant
For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=8
    
    