The following Water Outage has been Completed:
Outage:      ARC Water Meter Installation
Proposed By: David Sulouff
Start Time:  07/14/2023 08:00
End Time:    07/14/2023 12:00
Description/Impacts:
Water Meter Installation will require a water outage for roughly 4 hours to drain and modify piping.
Impacted Areas:
	ARC: Applied Research Center
For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=10
    
    