[Utility Outage] Cancelled Power Outage - 06/20/2023 07:00

Paul Powers powersp at jlab.org
Mon Jun 12 08:41:14 EDT 2023


The following Power Outage has been Cancelled:

Outage:      Bldg 12 F-Wing electrical outage
Proposed By: Paul Powers
Start Time:  06/20/2023 07:00
End Time:    06/20/2023 17:00

Description/Impacts:
Power outage for F-Wing to complete electrical PM for 2023.  This is already coordinated with the Data Center at their request.  This does not affect the rest of the CEBAF Center or the Kitchen.

Impacted Areas:
	Bldg 12: CEBAF Center

For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=4