[Utility Outage] Scheduled Power Outage - 03/24/2023 09:00
    todd kujawa 
    kujawa at jlab.org
       
    Thu Mar 23 12:29:13 EDT 2023
    
    
  
The following Power Outage has been Confirmed:
Outage:      CHL MCC-A breaker swap
Proposed By: todd kujawa
Start Time:  03/24/2023 09:00
End Time:    03/23/2023 11:00
Description/Impacts:
Shut down MCC-A to replace 90amp breaker with 125amp breaker to support temp cooling tower.
Working with Robert Norton from Cryo
Impacted Areas:
	Bldg 08: Central Helium Liquefier
For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=1
    
    