[Utility Outage] Completed Power Outage - 05/15/2023 09:00
    J. WIlloughby 
    jasonw at jlab.org
       
    Mon May 15 14:23:02 EDT 2023
    
    
  
The following Power Outage has been Completed:
Outage:      ARC Entire Building Normal Feed
Proposed By: J. WIlloughby
Start Time:  05/15/2023 09:00
End Time:    05/15/2023 10:00
Description/Impacts:
Remove normal feed from the main switchboard in the ARC.  This will remove all power from the entire building, except for items on the EM system - this would put the EM system on the generator.
Impacted Areas:
	ARC: Applied Research Center
For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=5
    
    
More information about the Fac_outages
mailing list