[Utility Outage] Proposed Power Outage - 11/27/2023 07:00
    todd kujawa 
    kujawa at jlab.org
       
    Tue Oct 31 11:30:07 EDT 2023
    
    
  
The following Power Outage has been Proposed:
Outage:      Hall A bunker DAQ area
Proposed By: todd kujawa
Start Time:  11/27/2023 07:00
End Time:    11/28/2023 16:00
Description/Impacts:
Turning off SWBD in order to add on a 3,000 amp switch.
The outage will affect the green concrete block bunker DAQ area.
Coordination with Hall leader Zachary.
DAQ electronics shall be secured/turned off (by owners) on or before Nov. 22 (before the Thanksgiving holiday break).
Impacted Areas:
	Bldg 101: Experimental Hall A
For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=4
    
    