The following Power Outage has been Proposed:
Outage: ESH BLDG UPS Power
Proposed By: J. WIlloughby
Start Time: 02/14/2024 06:30
End Time: 02/14/2024 08:30
Description/Impacts:
Remove power from the UPS-P1 panel to tie in new circuit. This will remove power from all circuits on UPS power (orange receptacles).
PYROLYSER
UPS REC. RM 31 EAST WALL
UPS REC. RM 31 SOUTH WALL
UPS REC. RM 31 WEST WALL
UPS REC. RM 31 NORTH WALL
UKPS REC. RM 20 EAST WALL
UPS REC. RM 20
REC. DATA RACK
REC. PYROLYSER COMPRESSOR
LIGHTING CONTROL PANEL POWER
UPS REC. RM 22 SOUTH WALL
UPS REC. RM 22 SOUTH WALL
UPS REC. RM 22 EAST WALL
UPS REC. RM 22 EAST WALL
UPS REC. RM 22 SOUTH WALL
UPS REC. RM 22 EAST WALL
UPS REC. RM 22 EAST WALL
UPS REC. RM 22 WEST WALL
UPS RE. RM 22 WEST WALL
Impacted Areas:
Bldg 52: EHS&Q Building
For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=12