The following Power Outage has been Completed:
Outage:      B58 shutdown DP-LAB-10, AP-LAB-16 SECT. 1, AP-LAB-16 SECT. 2
Proposed By: Howard Dunlap
Start Time:  07/10/2024 07:30
End Time:    07/10/2024 10:00
Description/Impacts:
Shutdown DP-LAB-10, AP-LAB-16 SECT. 1, & AP-LAB-16 SECT. 2 to add recs on top of UITF. 
Impacts: UITF, CLEANROOMS 1128 AND 1128A which have been notified and given approval. 
Impacted Areas:
	Bldg 58: Test Lab