The following Power Outage has been Completed:

Outage:      PANEL 58-AP-LAB-19 OUTAGE
Proposed By: Howard Dunlap
Start Time:  06/25/2024 09:00
End Time:    06/25/2024 12:00

Description/Impacts:
Shutdown PANEL 58-AP-LAB-19 to install and terminate breakers for newly installed receptacles on top of UITF cave. IMPACTS: See panel schedule 58-AP-LAB-19. Panel shutdown approved by Matt Polker, Max Bruker, and Gregory Blume. Max Bruker to notify Radcon. 


--

--

--


Impacted Areas:
	Bldg 58: Test Lab