[Utility Outage] Completed Power Outage - 10/09/2024 09:30
dunlap at jlab.org
dunlap at jlab.org
Wed Oct 9 12:31:24 EDT 2024
The following Power Outage has been Completed:
Outage: B96 SHUTDOWN PANEL C-UPL5
Proposed By: Howard Dunlap
Start Time: 10/09/2024 09:30
End Time: 10/09/2024 11:30
Description/Impacts:
Outlets need to be added. Will require a shutdown of panel C/UPL5. HELIUM VAC. PUMP, AVITRON PUMP, REFIDGERATOR CIRCULATOR, SCAT CHAMB. BLOWER MOTOR will be affected. See panel schedule for all the affected.
Impacted Areas:
Bldg 96: Experimental Hall C
For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=15
More information about the Fac_outages
mailing list