The following Power Outage has been Completed:
Outage:      Hall D 203-CH-L2 Outage
Proposed By: J. Willoughby
Start Time:  09/25/2024 08:00
End Time:    09/25/2024 12:00
Description/Impacts:
Cts did not fit - new plan for future retro-fit in design.  Power restored
Remove power from 203-CH-L2 panel to install CTs.  HDLIST 113400.
Please verify if your equipment is impacted during this outage and plan accordingly. 
Impacted Areas:
	Bldg 203: Experimental Hall D
For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=3
    
    