The following HVAC Outage has been Completed:
Outage: 28-AHU-4 PM SSC Main Building Air Handler Preventative Maintenance
Proposed By: Mike Sprouse
Start Time: 08/26/2025 07:00
End Time: 08/26/2025 09:00
Description/Impacts:
Performing preventative maintenance on the main air handler for Bldg. 28 - affects all areas.
Impacted Areas:
Bldg 28: SSC (VARC)