[Utility Outage] Completed Power Outage - 12/03/2025 09:00
Jasonw at jlab.org
Jasonw at jlab.org
Wed Dec 3 14:52:18 EST 2025
The following Power Outage has been Completed:
Outage: Injector Service Bldg B53
Proposed By: J. Willoughby
Start Time: 12/03/2025 09:00
End Time: 12/03/2025 13:00
Description/Impacts:
Remove power from B53 to install meter. Outage on 53-MDP-INJ. This is primary house power for the building. EM panel will not be impacted.
Impacted Areas:
Bldg 53: Injector Service
For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=25
More information about the Fac_outages
mailing list