[Utility Outage] Completed Power Outage - 02/12/2025 07:30
dunlap at jlab.org
dunlap at jlab.org
Wed Feb 12 14:50:01 EST 2025
The following Power Outage has been Completed:
Outage: B23 & B72 Outage
Proposed By: Howard Dunlap
Start Time: 02/12/2025 07:30
End Time: 02/12/2025 08:30
Description/Impacts:
Electrical Service Annual PM Bldgs. 23 & Bldg. 72. Exercise all panel breakers in the building. The entire building will be affected.
Impacted Areas:
Bldg 23: Experimental Staging Building
Bldg 72: Physics Storage
For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=1
More information about the Fac_outages
mailing list