[Utility Outage] Scheduled Power Outage - 01/31/2025 08:30
    dunlap at jlab.org 
    dunlap at jlab.org
       
    Fri Jan 31 07:48:19 EST 2025
    
    
  
The following Power Outage has been Confirmed:
Outage:      B36 Shut down Panel 36-L3
Proposed By: Howard Dunlap
Start Time:  01/31/2025 08:30
End Time:    01/31/2025 09:30
Description/Impacts:
Shutdown 36-L3 to terminate new outlets provided.  Outage confirmed by M.Beck. 
Impacted Areas:
	Bldg 36: General Purpose Building
For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=27
    
    
More information about the Fac_outages
mailing list