[Utility Outage] Completed Power Outage - 03/05/2025 07:00
    dunlap at jlab.org 
    dunlap at jlab.org
       
    Wed Mar  5 08:28:19 EST 2025
    
    
  
The following Power Outage has been Completed:
Outage:      B36 Outage Electrical Service Annual PM
Proposed By: Howard Dunlap
Start Time:  03/05/2025 07:00
End Time:    03/05/2025 08:30
Description/Impacts:
Electrical Service Annual PM Bldg. 36. Cycle all breakers in the bldg. Entire bldg. will be affected. B36 personnel have been notified & approved this outage. 
Impacted Areas:
	Bldg 36: General Purpose Building
For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=5
    
    
More information about the Fac_outages
mailing list