The following Power Outage has been Confirmed:
Outage: B12 Outage Electrical Service Annual PM (Cycle all electrical circuit breakers)
Proposed By: Howard Dunlap
Start Time: 03/21/2025 05:30
End Time: 03/21/2025 07:30
Description/Impacts:
Electrical Service Annual PM Bldg.12 (CEBAF). Facilities Maintenance Electrical (FME) will cycle all electrical circuit breakers in the bldg. with the exception of the Computer Center. OTHER THAN THE COMPUTER CENTER, THE ENTIRE BUILDING WILL BE AFFECTED. If you have electronics or sensitive equipment that would be impacted by this work, please power it down on Thursday evening 3/20/25 (or any time prior to the outage).
Impacted Areas:
Bldg 12: CEBAF Center
For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=3
More information about the Fac_outages