[Utility Outage] Proposed Power Outage - 06/03/2025 05:00
dunlap at jlab.org
dunlap at jlab.org
Thu May 29 13:43:33 EDT 2025
The following Power Outage has been Proposed:
Outage: Shut down Panels AP-2G-1 SECT. 1 & 2
Proposed By: Howard Dunlap
Start Time: 06/03/2025 05:00
End Time: 06/03/2025 07:30
Description/Impacts:
Shut down Panels AP-2G-1 SECT. 1 & 2 to terminate (2) dedicated circuits for 16a UPSs to serve computers at locations 58_2.2234 & 58_2.2231-13 per WO # 812837 & 812835. All Cubicles, offices, kitchenette, & copier receptacles on the 2ND FLOOR TEST LAB will be impacted.
Impacted Areas:
Bldg 58: Test Lab
For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=6
More information about the Fac_outages
mailing list